October 29, 2026
The Midtown Beach seawall runs 2,715 feet from Royal Palm Way south to Gulfstream Road. Along the top of it sits a narrow linear park of 42 coconut palms, two parallel sidewalks and the Worth Avenue Clock Tower, with South Ocean Boulevard on the other side. The wall is roughly a century old. Town staff now recommend closing the beach in front of it to the public for the entire replacement, from this winter until about spring 2028.
On the South End, the newly restored Phipps Ocean Park opens to the public on Thursday, Nov. 19. The two dates fall only weeks apart. Midtown is one of the town's two public beaches with lifeguards. If the full closure goes ahead, the other one, Phipps, will carry Palm Beach's public beach life for the rest of this season and all of the next.
The project is forecast to cost around $20 million and take about 18 months. Town Engineer Jake Hurley told the Town Council on Oct. 13 that staff want to start as soon as possible and use the winter months so construction stays within a single sea turtle nesting season, which runs from March 1 to Halloween, according to the Palm Beach Daily News. The sand recently added at Midtown is part of that plan. Crews would use it to build barriers on the ocean side so turtles don't nest inside the work zone.
Council members had raised the idea of building in stages so the beach could stay partly open. Staff said phasing could drive costs sharply higher and double the length of the job. It would also mean building and maintaining temporary beach entrances and setting up temporary restrooms near them. Hurley described a longer, staged project as more disruptive for nearby residents, while a full closure would keep the construction footprint smaller.
Council member Nicki McDonald explained the case for acting now in the same Daily News report. "The existing wall is approximately 100 years old, beyond its useful life and showing signs of failure," she said, adding that "important sanitary sewer infrastructure also runs beneath South Ocean Boulevard. Replacing the wall before a failure occurs is clearly the responsible course."
The street side of the site will look different too. Barriers will go up along the eastern parking spaces on South Ocean Boulevard, and the plans show them wrapped in screening printed with an ocean scene. South Ocean Boulevard will keep two-way traffic throughout. In the Palm Beach Civic Association's account of the Sept. 8 council meeting, Hurley predicted better traffic during construction because "we're not going to have individuals coming from off-island to park at the beach."
The full closure is still a staff recommendation, and the council still has decisions to make. These are the dates that shape this season:
| When | What | Where |
|---|---|---|
| Today, Oct. 29, 2 to 3 p.m. | Town public outreach meeting on the Midtown seawall | Town Hall, 360 S. County Road |
| As early as November | Design-builder Murray Logan Construction expected to report a guaranteed maximum price, along with drawings and a detailed schedule | Town Council |
| Nov. 19, 11 a.m. | Phipps Ocean Park ribbon cutting and grand opening, free and open to the public with registration | 2201 S. Ocean Blvd. |
| December, per staff's September timeline | Seawall construction begins | Royal Palm Way to Gulfstream Road |
| Spring 2028 | Forecast finish if the beach closes completely | Midtown Beach |
The Civic Association reported in September that today's meeting would focus on what construction means for residents, including the Midtown closure and traffic. The schedule has already shifted once. In August, Town Engineer Patricia Strayer described a start as early as January and up to two years of work. By September, staff were saying December and 18 months.
Phipps opens with history behind it. The Phipps family gave the land to the town in 1948 as a public beach and oceanfront park. The Preservation Foundation of Palm Beach, which led the redesign with the town, describes the restoration as turning a "long-underutilized space" into the public landscape that gift intended. The Palm Beach Daily News put the redevelopment at $31 million in April. At the time, the town was aiming for a September finish, though design changes had made that date less certain. The park has been closed since construction began. Only the tennis center and its parking lot reopened early, on Nov. 1, 2025.
The best-known piece is the Little Red Schoolhouse, built in 1886, which the Foundation calls Southeast Florida's first schoolhouse and the oldest landmark in Palm Beach. The plan moves it to higher ground near the dune so the Foundation can keep running its living-history program, which gives fourth graders a day of 1890s schooling in a one-room wooden classroom.
Raymond Jungles is the landscape architect, and Anne Fairfax and Richard Sammons are credited as the architects. According to the Foundation's campaign brochure and WLRN's reporting, the design calls for:
These are the planned features. Opening day on Nov. 19 will show how they turned out. Foundation Chairman Betsy Shiverick framed the project on the Foundation's Phipps Ocean Park page as one that "celebrates Palm Beach's natural heritage and creates exciting opportunities for outdoor learning and leisure."
The town has not published a list of other beach access points for the closure. One council member has already raised the issue. At the Sept. 8 meeting, Lew Crampton, a South End resident, said beachgoers who lose Midtown may crowd the beaches east of Sunrise Avenue and at Phipps. "Those folks are going to go south, and you are going to have a potential overload there," he said, according to the Civic Association. He wanted more discussion of partial versus full closure before the council decides.
So Phipps, a park the Foundation says the town underused for decades, reopens just as it may become Palm Beach's only open lifeguarded public beach. How the town handles parking, lifeguard staffing and day-to-day use at 2201 South Ocean Boulevard over the next 18 months will shape the public beach routine for everyone on the island. Those details are the ones to watch for at today's meeting and in the council sessions that follow.
Midtown should come back looking different. The town has budgeted around $4 million to remake the linear park next to the seawall, and that work would begin near the end of the seawall construction. Sean Twomey of Environmental Design Group drew the concept with input from the Garden Club of Palm Beach and from a public meeting at Town Hall on Dec. 11, 2025. As the Civic Association reported in August, the concept would:
The park plan still needs review by the town's Architectural Commission. The Daily News also reports pocket parks east of each intersection along that stretch. Strayer has said the town intends to save as many of the 42 coconut palms as it can, leaving them in place where possible and moving and replanting the rest. Some will likely need to be replaced. Council President Ted Cooney summed up the thinking in August, in remarks the Civic Association reported: "We ought to put things back nicer than we found them."
If you live in one of the oceanfront condominiums along South Ocean Boulevard, you will be close to all of this for the next season and a half, from the screened barriers to the new park that follows. Sharon Sweet follows these building-by-building and block-by-block changes closely, through the construction and after it. Schedule a private consultation for a quiet conversation about what the Midtown project means for your residence.